Diagram description

1. Detailed business case

Key activities: Appointing consultant team, developing strategic brief, options review, business case and project execution plan.

2. Implementation business case

Key activities: Confirms the strategic and economic cases, optimises value for money through supplier selection, sets out commercial arrangements, details management arrangements.

3. Design

Key activities: Concept design, preliminary design, developed design, detailed design.

4. Construction

Key activities: Site preparation, progressing the build, monitoring and quality evaluation, staff training and migration.

5. Fitout

Key activities: Procurement, installation and commissioning of furniture, fixtures and equipment.

06. Handover

Key activities: Commissioning, practical completion, code of compliance, asset transfer.